A brief progress report
Steady progress continues to be made on site. The foundation steel works were completed in February with the concrete floor slab poured in stages later in March. Walls are now starting to go up and the HAC is starting to take shape!
The recycling team has reached a milestone with the last of the recycled of materials taken out of the old Harbour Board building completed. We now have around 3,500 metres of beautiful native timber flooring. This will go into the galleries inside the HAC. We also have 18,000 bricks chipped and ready for supply to the site when needed.